Merrylands CBD Infrastructure Upgrade

Latest News

  • December 2024 update - Merrylands CBD works

    Endeavour Energy completed the work they needed to do in mid December. This will now allow the remaining construction work to proceed.

    The remaining work will proceed at the start of 2025, and is anticipated to complete in March 2025.

    The safety and wellbeing of our community will remain our highest priority and we will keep the community updated and informed as work progresses.

  • October 2024 update - Merrylands CBD works

    The Merrylands CBD Drainage and Infrastructure Upgrade is progressing with Addlestone Road now open to southbound traffic from Merrylands Road, improving the traffic flow and easing congestion around the project.