  • March 2025 - Merrylands CBD update

    Work in Addleston Road Merrylands is now complete. See below and in the gallery for images of the completed work.
  • February 2025 update - Merrylands CBD works

    Permanent road asphalt works on Addlestone Road/Merrylands Road Intersection, Merrylands will commence on Sunday 2 March 2025 from 7pm to 4am. For further details, 'Read More'.
  • December 2024 update - Merrylands CBD works

    Endeavour Energy completed the work they needed to do in mid December 2024.
  • October 2024 update - Merrylands CBD works

    The Merrylands CBD Drainage and Infrastructure Upgrade is progressing with Addlestone Road now open to southbound traffic from Merrylands Road, improving the traffic flow and easing congestion around the project. Read More to find out more details
  • August 2024 update - Merrylands CBD works

    Update on Endeavor Energy approvals for Addlestone Road.
  • July 2024 update - Merrylands CBD works

    Update on weather and utility delays.
  • June 2024 update - Merrylands CBD works

    Notice of delays due to utility delays.
  • February 2024 Update - works extended

    Update on works that have been completed to date.
  • July 2023 update - final stage work commencing

    The last remaining piece of infrastructure upgrade work to be completed is the construction of a new major stormwater culvert under Addlestone Rd near the intersection with Merrylands Road.
  • May 2023

    The works along Merrylands Rd between Burford Street and Cambridge Street are complete.