    Stage 1 (located between McFarlane Street and Main Lane)

    Stage 1 works commenced late October 2022 and works have begun in the areas outside of the zone of influence of Sydney Water's culvert.

    Sydney Water approval is required for works within the zone of influence of Sydney Water's culvert, and is anticipated to be received shortly.

    The pavers and street furniture for Stage 1 have been delivered.

    Photograph of Stage 1, taken on 20 December 2022.

    Stage 2 (between Main Lane and Merrylands Road)

    The Construction Certificate for Stage 2 has been issued and civil works for Stage 2 commenced mid-January 2023.

    Excavation for the tree vaults now completed.

    Photograph of Stage 2, taken on 19 January 2023.